Factory Acceptance Testing (FAT): Complete Guide for Manufacturers
Learn how to conduct effective Factory Acceptance Testing. Discover procedures, checklists, and best practices for equipment and system verification.
Factory Acceptance Testing (FAT): Complete Guide for Manufacturers
Meta Description: Learn how to conduct effective Factory Acceptance Testing. Discover procedures, checklists, and best practices for equipment and system verification.
Introduction
Factory Acceptance Testing (FAT) is the process of verifying that equipment or systems meet specified requirements before shipment to the customer's site. Proper FAT prevents problems during installation and commissioning.
What Is Factory Acceptance Testing?
FAT is a series of tests conducted at the vendor's facility to verify that the equipment or system meets all requirements and specifications.
┌─────────────────────────────────────────────────────────────────┐
│ FAT in the Project Lifecycle │
├─────────────────────────────────────────────────────────────────┤
│ │
│ REQUIREMENTS → DESIGN → BUILD → FAT → SHIP → SAT → OPERATION │
│ │ │
│ ▼ │
│ Verify at Vendor │
│ Before Shipping │
│ Easier to Fix │
│ │
│ FAT: Factory Acceptance Test (at vendor) │
│ SAT: Site Acceptance Test (at customer site) │
│ │
└─────────────────────────────────────────────────────────────────┘
Why FAT Is Important
Benefits of Proper FAT
| Benefit | Description |
|---|---|
| Early Problem Detection | Find issues before shipping |
| Easier Corrections | Fix problems at vendor facility |
| Reduced Site Issues | Fewer problems during installation |
| Verification | Confirms requirements are met |
| Documentation | Establishes baseline |
| Training | Hands-on opportunity for operators |
| Risk Reduction | Mitigates project risk |
FAT Process
Phase 1: Preparation
┌─────────────────────────────────────────────────────────────────┐
│ FAT Preparation Checklist │
├─────────────────────────────────────────────────────────────────┤
│ │
│ REQUIREMENTS │
│ ☐ Specifications defined │
│ ☐ Acceptance criteria established │
│ ☐ Test procedures documented │
│ ☐ Success criteria clear │
│ │
│ LOGISTICS │
│ ☐ FAT scheduled │
│ ☐ Attendees identified (customer, vendor, integrator) │
│ ☐ Travel arrangements │
│ ☐ Duration planned (typically 1-5 days) │
│ │
│ DOCUMENTATION │
│ ☐ Test procedures prepared │
│ ☐ Checklists created │
│ ☐ Forms for results recording │
│ ☐ Issue tracking prepared │
│ │
│ EQUIPMENT │
│ ☐ Test equipment available │
│ ☐ Measurement tools calibrated │
│ ☐ Required materials available │
│ ☐ Safety equipment provided │
│ │
└─────────────────────────────────────────────────────────────────┘
Phase 2: FAT Execution
FAT TEST SEQUENCE:
1. Visual Inspection
2. Documentation Review
3. Static Tests
4. Dynamic Tests
5. Operational Tests
6. Integration Tests
7. Performance Verification
8. Safety Testing
9. Cleanup/Restore
10. Results Review and Sign-off
Phase 3: Documentation
FAT DOCUMENTATION DELIVERABLES:
☐ FAT plan (pre-approved)
☐ Test procedures
☐ Test results
☐ Issues list (open and closed)
☐ As-built documentation
☐ Calibration certificates
☐ Software/firmware versions
☐ FAT report with sign-off
FAT Test Categories
1. Visual Inspection
INSPECTION CHECKLIST:
☐ Equipment matches specifications
☐ Construction quality acceptable
☐ Proper materials used
☐ No visible damage
☐ Adequate access for maintenance
☐ Safety guards installed
☐ Labels and nameplates present
☐ Paint and finish acceptable
☐ Proper grounding
☐ Conduit and wiring neat and secure
2. Documentation Review
DOCUMENTATION CHECKLIST:
☐ Manuals provided (operation, maintenance)
☐ Drawings (electrical, mechanical, layout)
☐ Bill of materials
☐ Spare parts list
☐ Software documentation
☐ Certifications (CE, UL, etc.)
☐ Calibration certificates
☐ Test reports
☐ Data sheets
☐ Safety documentation
3. Functional Testing
FUNCTIONAL TESTS:
☐ Individual component operation
☐ Sequence verification
☐ Interlock testing
☐ Alarm and indication testing
☐ Control system functionality
☐ HMI/SCADA interface testing
☐ Communication testing
☐ Power supply verification
☐ I/O verification
4. Performance Testing
PERFORMANCE VERIFICATION:
☐ Capacity verification
☐ Speed verification
☐ Accuracy verification
☐ Repeatability testing
☐ Throughput verification
☐ Quality verification
☐ Efficiency verification
☐ Environmental condition testing
5. Safety Testing
SAFETY VERIFICATION:
☐ Emergency stop testing
☐ Safety circuit testing
☐ Guard switch verification
☐ Light curtain testing
☐ Pressure relief verification
☐ Temperature protection testing
☐ Lockout/tagout points verified
☐ Warning labels verification
☐ Safety distance verification
FAT Common Findings
Typical Issues Discovered
| Category | Typical Findings |
|---|---|
| Documentation | Missing manuals, incorrect drawings |
| Wiring | Loose connections, wrong gauge |
| Labeling | Missing or incorrect labels |
| Software | Version mismatch, bugs |
| Safety | E-brake accessibility, guard gaps |
| Performance | Speed/capacity slightly off spec |
| Integration | Communication issues |
FAT vs. SAT
| Aspect | FAT (Factory) | SAT (Site) |
|---|---|---|
| Location | Vendor facility | Customer site |
| Conditions | Simulated or actual load | Actual production |
| Corrections | Easy to make | More difficult |
| Focus | Equipment verification | System verification |
| Attendees | Vendor, customer | Vendor, customer, contractors |
FAT Checklist Template
Mechanical Equipment
EQUIPMENT: _______________________ DATE: ________
VENDOR: ________________________ FAT #: ________
VISUAL INSPECTION
☐ Dimensions per drawing
☐ Materials of construction correct
☐ Welds acceptable
☐ Fasteners correct and tight
☐ Alignment acceptable
☐ Bearings/lubrication correct
☐ Guards installed properly
☐ Nameplates installed
FUNCTIONAL TESTS
☐ Manual operation successful
☐ Automatic operation successful
☐ Sequence correct
☐ Interlocks function
☐ Emergency stop works
☐ Alarms function correctly
PERFORMANCE VERIFICATION
☐ Speed meets specification
☐ Capacity meets specification
☐ Accuracy meets specification
☐ Repeatability acceptable
DOCUMENTATION
☐ Manual provided
☐ Drawings provided
☐ Spare parts list provided
☐ Calibration certs provided
ISSUES:
_______________________________________________________________
_______________________________________________________________
OVERALL RESULT: ☐ PASS ☐ PASS WITH MINOR ☐ FAIL
SIGNATURES:
Vendor: _________________ Date: ________
Customer: _______________ Date: ________
Best Practices
For Successful FAT
-
Plan Thoroughly
- Detailed test procedures
- Clear acceptance criteria
- All stakeholders aligned
-
Attend in Person
- See equipment operate
- Meet vendor team
- Training opportunity
-
Test Realistically
- Simulate actual conditions
- Test with real materials if possible
- Verify all functions
-
Document Everything
- Record all results
- Photograph equipment
- Note all issues
-
Follow Up Issues
- Ensure all problems resolved
- Re-test as needed
- Document resolution
Common FAT Mistakes
| Mistake | Impact | Prevention |
|---|---|---|
| Poor preparation | Wasted time, missed tests | Detailed planning |
| Vague acceptance criteria | Disputes over results | Clear, measurable criteria |
| Insufficient time | Rushed testing | Adequate time allocation |
| Not attending | Missed learning, surprises | Customer attendance |
| Skipping tests | Undiscovered problems | Complete all planned tests |
| Poor documentation | No baseline, confusion | Thorough documentation |
FAT for Different Equipment
Control Systems
CONTROL SYSTEM FAT:
☐ I/O testing (all points)
☐ HMI/SCADA testing
☐ Alarm verification
☐ Trend/logging verification
☐ Recipe testing
☐ Security testing
☐ Network communication
☐ Backup/restore testing
☐ Redundancy testing
Mechanical Equipment
MECHANICAL EQUIPMENT FAT:
☐ Dimensional verification
☐ Alignment checks
☐ Run-in testing
☐ Load testing
☐ Vibration testing
☐ Temperature verification
☐ Noise level verification
Software Systems
SOFTWARE FAT:
☐ Installation testing
☐ Functionality testing
☐ Integration testing
☐ Performance testing
☐ Security testing
☐ User acceptance testing
☐ Data migration testing
Conclusion
Factory Acceptance Testing is a critical quality gate that prevents problems later when corrections are more expensive. Thorough preparation, clear acceptance criteria, and complete testing ensure successful FAT results.
Need help planning your FAT? Contact us for FAT procedure development and support.
Related Topics: Site Acceptance Testing, Commissioning, Equipment Qualification