Back to Blog
Lean Manufacturing

Production Planning and Scheduling: Complete Manufacturing Guide

Master production planning and scheduling in manufacturing. Learn strategies, methods, and tools for optimizing capacity and meeting customer demand.

8 min read
Share:

Production Planning and Scheduling: Complete Manufacturing Guide

Meta Description: Master production planning and scheduling in manufacturing. Learn strategies, methods, and tools for optimizing capacity and meeting customer demand.


Introduction

Production planning and scheduling (PPS) is the backbone of manufacturing operations, determining what to produce, when to produce it, and what resources are needed. Effective PPS balances customer demand with production capacity while minimizing costs and maximizing efficiency.

What Is Production Planning?

Production planning determines what, how much, and when to produce based on demand forecasts, capacity constraints, and inventory policies.

The Planning Hierarchy

┌─────────────────────────────────────────────────────────────────┐
│              Production Planning Hierarchy                       │
├─────────────────────────────────────────────────────────────────┤
│                                                                 │
│  STRATEGIC PLANNING (Long-term: 1-5 years)                     │
│  • Capacity planning                                            │
│  • Facility planning                                            │
│  • Technology investment                                        │
│  • Make vs. buy decisions                                       │
│                                                                 │
│  TACTICAL PLANNING (Medium-term: 6-18 months)                   │
│  • Aggregate planning                                          │
│  • Production budgeting                                         │
│  • Workforce planning                                           │
│  • Material planning                                            │
│                                                                 │
│  OPERATIONAL PLANNING (Short-term: days-weeks)                  │
│  • Master scheduling                                           │
│  • Material requirements planning                               │
│  • Capacity requirements planning                               │
│  • Final assembly scheduling                                    │
│                                                                 │
│  SCHEDULING (Very short-term: hours-days)                       │
│  • Shop floor control                                           │
│  • Sequencing                                                   │
│  • Dispatching                                                  │
│                                                                 │
└─────────────────────────────────────────────────────────────────┘

Production Planning Steps

Step 1: Forecast Demand

Predict future customer demand:

Forecasting MethodBest ForTime Horizon
JudgmentNew products, strategicLong-term
Market ResearchNew products, featuresMedium-term
Time SeriesStable demandShort-medium
Causal ModelsDemand driversMedium-term
CollaborativeSupply chain alignmentMedium-term

Step 2: Determine Production Capacity

Assess available resources:

Capacity Elements:
• Equipment capacity (hours available)
• Labor capacity (skills, shifts)
• Material availability
• Storage capacity
• Budget constraints

Theoretical Capacity =
  Available time × Production rate

Rated Capacity =
  Theoretical capacity × Efficiency rate

Demonstrated Capacity =
  Actual production achieved

Step 3: Compare Capacity with Demand

Identify gaps and develop strategies:

SituationStrategy
Demand < CapacityReduce shifts, build inventory, develop new markets
Demand ≈ CapacityMaintain, focus on efficiency
Demand > CapacityOvertime, subcontract, add capacity, backorder

Step 4: Develop Production Plan

Create the plan:

Production Plan Elements:
• What products to produce
• How much to produce
• When to produce
• Where to produce (which facility)
• Resources required
• Target costs

Step 5: Monitor and Adjust

Track performance and adjust:

  • Compare actual vs. plan
  • Identify variances
  • Adjust plan as needed
  • Communicate changes

Master Production Schedule (MPS)

The MPS is the build plan for end items:

┌─────────────────────────────────────────────────────────────────┐
│                    Master Production Schedule                    │
├─────────────────────────────────────────────────────────────────┤
│                                                                 │
│  Product: Widget A                                             │
│  Lot Size: 100                                                 │
│  Lead Time: 2 weeks                                            │
│                                                                 │
│  Week:        1    2    3    4    5    6    7    8             │
│  ────────────────────────────────────────────────────────────  │
│  Forecast    50   50   60   60   70   70   80   80             │
│  Orders      45   55   40   65   50   60   --   --             │
│  PAB         80   30   70   10   40   70   90   10             │
│  MPS        --    --   100   --   100  100  100   --           │
│  ATP         35   --    50   --    50   40   100   --           │
│                                                                 │
│  PAB = Projected Available Balance                              │
│  ATP = Available to Promise                                     │
│                                                                 │
└─────────────────────────────────────────────────────────────────┘

Material Requirements Planning (MRP)

MRP calculates materials needed based on MPS and bill of materials:

MRP Inputs

  1. Master Production Schedule - What to make
  2. Bill of Materials - What's in each product
  3. Inventory Records - What's on hand
  4. Lead Times - How long items take to arrive

MRP Logic

For each component:
  Gross Requirements = MPS quantity × BOM quantity
  Net Requirements = Gross Requirements - On Hand - On Order
  Planned Orders = Net Requirements (adjusted for lot size)
  Planned Order Release = Planned Orders - Lead Time

Scheduling Methods

1. Forward Scheduling

Schedule from start date:

  • Used for make-to-order
  • Calculates earliest completion
  • Considers capacity immediately

2. Backward Scheduling

Schedule from required due date:

  • Used for make-to-stock
  • Calculates latest start time
  • Ensures on-time delivery

3. Finite Scheduling

Considers capacity constraints:

  • More accurate but complex
  • Requires good data
  • Software often needed

4. Infinite Scheduling

Assumes unlimited capacity:

  • Simpler calculation
  • Capacity issues identified later
  • Requires manual leveling

5. Optimized Production Technology (OPT)

Focus on bottlenecks:

  • Identify constraint
  • Subordinate everything to constraint
  • Elevate constraint performance
  • Repeat as constraint moves

Sequencing Rules

Job Shop Sequencing

When multiple jobs compete for same resources:

RuleDescriptionBest For
FCFSFirst Come, First ServedSimple, fair
SPTShortest Processing TimeMinimizing average completion
EDDEarliest Due DateMeeting due dates
CRCritical Ratio (Time left/Work left)Managing lateness
Johnson's RuleTwo-machine optimizationFlow shops

Scheduling Challenges

Common Challenges

ChallengeCauseSolution
BottlenecksUnbalanced capacityIdentify and optimize constraint
Setup TimesChangeovers reduce capacitySMED, family grouping
Rush OrdersDisrupt scheduleReserve capacity, premium pricing
Machine BreakdownsUnplanned downtimePreventive maintenance, buffer
Material ShortagesSupply issuesSafety stock, reliable suppliers
Employee AbsencesLabor availabilityCross-training, flexible staffing

Advanced Scheduling Techniques

1. Theory of Constraints (TOC)

Five focusing steps:

  1. Identify the constraint
  2. Exploit the constraint
  3. Subordinate everything else
  4. Elevate the constraint
  5. Repeat if constraint moves

2. Drum-Buffer-Rope (DBR)

TOC scheduling method:

  • Drum: The constraint sets the pace
  • Buffer: Protection before the constraint
  • Rope: Communication/tie to constraint

3. Lean Scheduling

Heijunka (leveling):

  • Mixed model production
  • leveled production volume
  • Standardized work
  • Pull system (Kanban)

4. Advanced Planning and Scheduling (APS)

Software-based optimization:

  • Constraint-based scheduling
  • Real-time updates
  • What-if analysis
  • Multi-objective optimization

Production Planning KPIs

Key Metrics

KPIFormulaTarget
Schedule AttainmentOrders completed on schedule / Total orders>95%
Schedule AdherencePlanned vs. actual sequence>90%
Capacity UtilizationActual output / Rated capacity80-85%
Make-to-Order Cycle TimeOrder receipt to shipmentMinimize
ThroughputUnits produced per time periodMaximize
WIP InventoryValue of work in processMinimize
On-Time DeliveryOn-time orders / Total orders>95%

Digital Transformation in PPS

Industry 4.0 Technologies

┌─────────────────────────────────────────────────────────────────┐
│                    Modern PPS Capabilities                      │
├─────────────────────────────────────────────────────────────────┤
│                                                                 │
│  REAL-TIME DATA                                                │
│  • Machine status                                              │
│  • Production progress                                         │
│  • Material availability                                        │
│  • Labor presence                                              │
│                                                                 │
│  AUTOMATIC RESCHEDULING                                        │
│  • Event-driven updates                                        │
│  • Real-time constraint checking                               │
│  • Automatic notifications                                     │
│                                                                 │
│  AI AND OPTIMIZATION                                           │
│  • Machine learning for better scheduling                       │
│  • Predictive disruption detection                             │
│  • Automated decision making                                   │
│                                                                 │
│  INTEGRATION                                                   │
│  • Connected to MES, ERP, SCM                                  │
│  • Single source of truth                                      │
│  • End-to-end visibility                                       │
│                                                                 │
└─────────────────────────────────────────────────────────────────┘

Best Practices

1. Sales and Operations Planning (S&OP)

Align supply and demand:

  • Monthly cross-functional meeting
  • Review demand and supply
  • Make trade-off decisions
  • Update financial plans
  • One set of numbers

2. Frozen vs. Flexible Planning

Time fence approach:

  • Frozen zone: Immediate future, no changes
  • Slushy zone: Trade-offs allowed
  • Liquid zone: Flexible planning

3. Capacity Buffers

Plan for uncertainty:

  • Safety capacity (similar to safety stock)
  • Overtime availability
  • Subcontractor relationships
  • Flexible workforce

4. Continuous Improvement

Regularly improve planning:

  • Track forecast accuracy
  • Measure schedule adherence
  • Analyze variances
  • Update planning parameters
  • Refine planning logic

Conclusion

Effective production planning and scheduling balances customer demand with production capacity while minimizing costs. Success requires accurate data, reliable processes, continuous improvement, and integration across the organization.

Need to improve your planning and scheduling? Contact us for an assessment and optimization roadmap.


Related Topics: S&OP Implementation Guide, Capacity Planning, Demand Forecasting Methods

#mes#erp#lean#kanban